Tag Archives: Bank Guarantee

RTI- Corruption in LRSAM Project

To,                                                                                                                    17th April 2014
Shri Pritam Dutta, IDAS,
ACDA, CPIO,CVO,
O/o PCDA (R&D), West Block-V,
R K PURAM,
NEW DELHI- 110066              

Hello,
Kindly provide me with the following information requested under the purview of the Right to Information Act, 2005 in respect  of LRSAM Project, DRDL’s demand of  Design, Manufacturing, Supply, Erection and Commissioning of Detachable Integrated Logistics Store Enclosure vide Demand No. DRDL/LRS/26/98P/13/049 Demand Dated 31/12/13. It is observed that M/s Trinetra Constructions already started construction on the site against above demand well before (almost two months) supply order is not given to firm. The firm already erected the structure and work in progress the store was constructed and wall plaster is in progress.

The demand was raised vide Demand No.  (DRDL/LRS/26/98P/13/049) dated 31.12.13  by sh V. Venkateswarlu , Scientist – D, LRSAM Project, DRDL SO Value with TAX (Rs.) 29925000.00 Firm Name M/s Trinetra Constructions  Address 17-1-388/77/B, Lakshmi Nagar Colony, Saidabad , HYDERABAD The firm submitted the Bank Guarantee of  Rs 2850000  vide Andhra Bank  Guarantee No.35214IGPER0004 dated 13.03.14 As per the bank guarantee dates  and enclosed photo of constructions anyone can understood the work was started very early before the date of bank i.e 13.03.14. Your rep Sh   Ved Veer Arya , IDAS, finance officer , missile complex ( DRDL,ASL, was participated in the processing of the case. The matter is directory related with corruption and it seems that PCDA rep closed his eyes because the rate of construction of required store Enclosure is five time higher.

  1. Names and address of  firms who were invited for said demand as the case was dealt in limited tender mode
  2. The copies of quotations received from firms against said demand
  3. Copy of authority letter (other than supply order) given to M/s Trinetra Constructions enters and starts the construction the restricted area by competent LRSAM officials.
  4. Date of starting construction by M/s Trinetra Constructions against above said demand.
  5. Certified copies of last three years (April 2010 to March 2013) orders given by DRDL to M/s Trinetra Constructions.
  6. Provide the number of supply orders placed to M/s Trinetra Constructions in April 2011 to March 2014 processed by CDA, Hyderabad.

Note : Matter is directly related to corruption and not exempted under Section 24 (1) as a proof the photos of above said   Detachable Integrated Logistics Store Enclosure are enclosed.

Please follow the provision of section 6(3) of the Act.

 

Regards
Prabhu  Dandriyal,
21-Sunderwala, Raipur, Dehradun -248008 
Phone 0135- 2787750, Mobile- 9411114879,
e-mail id prabhudoon@gmail.com  website www.corruptionindrdo.com

Enclosed – Photos of construction in different stages

Registration Number            MODEF/R/2014/60770