HAL’s Light Combat Aircraft project to come under IAF control

Dinakar Peri   NEW DELHI, AUGUST 04, 2018 THE HINDU

 

Slow takeoff: The development of the Tejas-Mk 1A with specific enhancements has been delayed.

To prevent time and cost overruns, the IAF will soon have effective control over India’s indigenous LCA programme
The government is poised to hand over control of the Bengaluru division of State-owned Hindustan Aeronautics Limited (HAL) to the Indian Air Force (IAF). This is to prevent more time and cost overruns on the indigenous Light Combat Aircraft (LCA) project. This comes at a particularly crucial time as the next phase of the LCA project, development of the MK2 variant, as well as the country’s next fighter aircraft programme, the Advanced Medium Combat Aircraft (AMCA), begin to take shape.

“The government has given the go ahead to hand over the entire Bengaluru complex of HAL to the IAF. With this, the fixed wing aircraft division will come under the IAF. The modalities are being worked out,” an official source told this reporter of the process that may take a few months.

HAL resists
HAL manufactures and assembles a range of aircraft and helicopters. However, it has faced criticism for its time and cost overruns and lack of professionalism in project execution. HAL has opposed this move for a long time, fearing erosion of its autonomy.

The LCA programme was sanctioned in 1983 and the aircraft made its first flight in 2001. The IAF had signed two contracts with HAL, one for 20 aircraft in the Initial Operational Clearance (IOC) configuration signed on March 31, 2006, to be completed by December 2011, and another for 20 aircraft in the Final Operational Clearance (FOC) standard signed on December 23, 2010, which was to be completed by 2016. It is in the process of ordering 83 jets in the Mk 1A configuration.

The IAF constituted the first LCA squadron with just two aircraft in 2016 and, as of July 2018, has inducted only nine aircraft. Tejas has once again missed the FOC in June and the development of the Tejas-Mk 1A with specific enhancements has been delayed. With this development, HAL’s aircraft division will be headed by a serving three-star officer or an Air Marshal of the IAF, and effectively give the IAF control over the country’s indigenous LCA project.

In addition, three institutions — Aeronautical Development Agency (ADA), Aeronautical Development Establishment (ADE) and Gas Turbine Research Establishment (GTRE) — which are under the Defence Research Development Organisation (DRDO) are likely to be brought under the direct control of the Chief of the Air Staff. Thus, the entire development cycle of the LCA will have the IAF’s oversight and will ensure timely execution and prevent blame games over delays, the source observed. Details of the specific contours of the move are awaited.

‘Long overdue’
“The IAF should have taken over the LCA programme two decades back, but [it is] good it’s happening at least now,” said Air Marshal M. Matheswaran (Retd), who oversaw the IAF’s fighter procurement in the past. He felt that to make a real difference, the IAF should get the entire cycle under its control, from design, standardisation, production and supply chain. Otherwise, just having one officer at the helm will not change things much, he added.

“Production for 20 FOC aircraft will be taken up after FOC clearance by the ADA, for which the current target is December 2018,” Minister of State for Defence Subhash Bhamre said in a written reply in the Rajya Sabha last week.

However, a Defence Ministry official said this is likely to be delayed by another six months as several parameters like gun firing, air-to-air refuelling and new data-linked software defined radios, among others, are yet to be validated. The IAF wants new data links as a standard feature on the FOC variant as communications are an essential feature for an aircraft to operate in a network-centric environment.

HAL is setting up a second assembly line to ramp up production from eight to 16 aircraft a year, in addition to outsourcing major modules to private partners.

Design reboot
The LCA is powered by an American GE-404 engine, which the IAF has stated is underpowered. This is to be corrected in the LCA-Mk2 which would be a larger aircraft powered by the GE-414 engine producing 98kN thrust compared to 84kN thrust of the current engine.

“The design change has been launched sometime back. We don’t want just some superficial changes, but a real increase in performance. The target is to meet or exceed the Mirage aircraft in performance,” an IAF official said.

To accommodate the larger and more powerful engine, which also needs more fuel, requires a larger wingspan for the aircraft. This calls for a major design and engineering effort.

“There are concerns and challenges but it is doable,” the officer noted.

The first prototype of the Mk2 is expected to make its debut flight in 2022-23, and complete the IOC and FOC approvals in the next five years. The current target is to have the first squadron ready by 2028.

The IAF intends to have several squadrons of the LCA-Mk2 as it has to replace three Mirage squadrons, three Mig-29 squadrons and six Jaguar squadrons. A squadron typically has about 18 aircraft, 16 fighters and two trainers. However, this can vary, depending on the type of aircraft and the necessity.

LCA will not be able to penetrate enemy lines

Kalyan Ray, New Delhi, May 08,2015, DHNS:
LCA DH 8 may 2015The indigenous Tejas light combat aircraft (LCA) will experience a major handicap in defeating the enemy due to non-availability and poor performance of three electronic warfare instruments, developed by Indian agencies.

During the trial, the all-important counter measure dispensing system that protects the aircraft against radar and heat-seeking missiles, could not do its job properly, leaving the jet with poor defence. The system was developed by , Hyderabad-based Bharat Dynamics Limited.

It was not the only faltering system on-board the LCA. The self protection jammer that blocks the enemy radar was too big to be fitted into the Mark-I version of the LCA and the radar warning receiver, which alerts the pilots on hostile enemy signals, perform poorly. Both were developed by Bangaluru-based Defence Avionics Research Establishment.

“LCA Mark-I remains deficient in full electronic warfare capabilities as specified in the Air Staff Requirement (ASR),” the Comptroller and Auditor General (CAG) says in a review report that was tabled in Parliament on Friday.

The aircraft, which achieved initial operational clearances on December 2013, has as many as 53 shortfalls from the specifications drawn in the ASR.

Some of the shortcomings like increased weight, reduced internal fuel capacity, pilot protection from the front and reduced speed are to be addressed in the Mark-II version that was taken up by the Aeronautical Development Agency in 2009 and scheduled for completion in 2018.

Even after 30 years, the LCA could get only the initial operational clearance (IOC) in December 2013. The full operational clearance (FOC) is now targeted in December, 2015.

The cost is also rising all these years. What began as a Rs 560 crore programme in 1983 has now gone up by almost twenty times. The financial package for LCA now stands at Rs 8294 crore.

The auditor also criticised the Defence Ministry for awarding two commercial contracts to Hindustan Aeronautics Limited (HAL) in 2006 and 2010 for delivering 20 fighter planes in each contract in the IOC and FOC configurations respectively to the IAF.

Both were termed premature because in 2006 LCA design was nowhere near finalisation, whereas in 2010 HAL was yet to supply any aircraft to the force as per the previous contract. Even now, the IAF is not in a position to operationalise the LCA squadron in the absence of a trainer aircraft. Moreover, HAL’s production capacity – four aircraft per year – is only half of what the government wants.
DH News Service

Don’t delay Light Combat Aircraft project: Anthony to DRDO

Rajat Pandit, TNN Nov 6, 2013, 08.19PM IST
NEW DELHI: Defence minister A K Antony on Wednesday directed the DRDO to ensure that the operational deadlines for the Tejas Light Combat Aircraft, first sanctioned 30 years to replace the ageing MiG-21s, are not delayed yet again.

Addressing the parliamentary consultative committee on defence, Antony said the under-development indigenous fighter’s initial operational clearance (IOC) planned for next month and the final operational clearance (FOC) in December 2014 should be “completed on schedule”.With DRDO currently handling as many as 532 projects, the minister asked DRDO to “mainly concentrate on high-end research, particularly in critical and strategic areas”. DRDO should invest more time and resources in fundamental research, lay more emphasis on major mission-mode programmes for the armed forces and pool together resources and talent available in academic and other R&D institutions, he said.

The long-running developmental sagas of the Tejas fighter and Arjun main-battle tank have come to symbolize the huge delays and cost-overruns dogging virtually all major projects of DRDO. While the MPs lauded DRDO’s success in the field of missiles, they were “bitterly critical” of the delay in such projects.

As earlier reported by TOI, the single-engine Tejas is unlikely to become fully combat-worthy anytime before end-2015. When the Tejas project was first sanctioned in 1983, the initial project cost was pegged at Rs 560 crore. The overall programme will now cost upwards of Rs 25,000 crore if the naval variant, trainer and the failed Kaveri engine are also taken into account.

It was in January 2011 that Tejas got IOC-I, which was initially heralded as the “full and final IOC” by the combine of DRDO, Aeronautical Development Agency and Hindustan Aeronautics Ltd till better sense prevailed. The fighter can be certified as fully airworthy only after it passes the IOC-II stage.

The light-weight Tejas will be ready to go to war only after the FOC, which will include integration of all weapons and other systems to ensure it can fire guns, rockets, laser-guided bombs and BVR (beyond visual range) missiles as well as undergo air-to-air refuelling.

Tejas project gets wings again under new DRDO chief

By Anantha Krishnan M | ENS – BANGALORE 01st June 2013 12:33 PM                 – THE NEW INDIAN EXPRESSavinash The Defence Research and Development Organisation’s (DRDO) new boss Dr Avinash Chander has put India’s fighter jet project Tejas on his radar, with a possible mission to jettison it out of the current turbulence. In an interview to Express on Friday, soon after New Delhi officially handed over the mandate to pilot DRDO for the next three years, Avinash said that completing the Initial Operational Clearance (IOC) of Tejas by September this year and attaining the Final Operational Clearance (FOC) by the end of 2014, are two primary targets he has already set. “After finishing the taking over formalities, I am catching the first available flight to Bangalore to review the project. I am absolutely aware of the issues that are dogging the project and I would now want to see it from close quarters, what the delays are. The Tejas’ IOC and FOC cannot be postponed any further,” said Avinash, who will also double up as the Scientific Advisor to Defence Minister. He said the induction of India’s long-range ballistic missile Agni-V and development of 155-mm gun are other projects that would get his immediate attention. Saying that his task is cut out with many projects reeling under time overruns, Avinash promised to turn around DRDO into a delivery-oriented unit. “There are grey areas still, despite our efforts to stick to the deadline. We are lagging behind in directive energy systems such as high-energy electro-magnetic lasers. We also need to gear up on the materials front,” said the missile scientist. We have proven our abilities with multiple missile programmes and we need to emulate the same in other projects as well,” said the 62-and-a-half-year-old DRDO chief. He said DRDO will be restructured to catch up with the challenges of modern times. “I will take everything one step at a time. I am aware that we need to create the ‘Brand DRDO’ image,” he said It will be a collective team effort. The idea is to take DRDO to the next level. I will ensure that the confidence of users in DRDO will be always high, Avinash said. Incidentally, Avinash will be the second man after former president Dr A P J Abdul Kalam, who will serve as the DRDO chief beyond 65 years.